Cable Laying Guide: Key Points for Direct Burial, Conduit, and Tray Installation
Whether underground, in conduit, or on trays, the safe operation of cables depends on standardized laying techniques.
Cable laying is an essential and critical component of power systems, directly impacting power supply reliability, safety, and ease of operation and maintenance. According to statistics, nearly 40% of cable failures are related to improper laying methods.
Different environmental conditions require different cable laying methods, each with its own unique technical specifications and quality control points. This article will provide a detailed introduction to the three common cable laying methods: direct burial, conduit, and tray installation, to help you fully understand the regulatory requirements for each technique.
---
01 Direct Burial: Technical Details of Concealed Underground Projects
Direct burial is a traditional method of burying cables directly underground. Due to its low investment cost, convenient construction, and excellent heat dissipation, it is widely used in accessible underground areas such as suburban areas and farmland.
However, this laying method also has limitations: susceptibility to underground corrosive substances and difficulty in troubleshooting. Therefore, strict adherence to technical specifications is essential.
Route selection is paramount for direct burial cable installation. Chemical corrosion zones, stray current zones, and termite infestation zones must be avoided. A safe distance from heat sources must also be maintained. Parallel installation with heat pipes is strictly prohibited. When paralleling with heat pipes, the clear distance should be greater than 2000mm, and the clear distance at intersections should be greater than 500mm.
The burial depth directly impacts cable safety. In non-frozen areas, the depth from the cable sheath to the ground must be no less than 0.7 meters; in farmland, no less than 1 meter; and in cold regions, the cable must be buried below the permafrost layer.
When direct burial cables are installed in non-frozen areas, the distance from the cable sheath to the foundation of underground structures must be no less than 0.3 meters.
When selecting cables, armored cables are preferred for direct burial to enhance mechanical protection. In locations where mechanical damage is unlikely, unarmored plastic-sheathed cables can also be used.
In soils prone to displacement, such as quicksand and backfill, steel-wire armored cables are required.
Regarding cable laying techniques, the bottom of the cable trench must be soft soil, free of rocks or other hard debris. A 100mm thick layer of sand or soft soil should be laid evenly above and below the cables, then covered with a protective layer such as a concrete protective plate.
The protective plate should extend 50mm beyond the cable on both sides.
Cable spacing is also crucial. When cables below 10kV are laid in parallel, a spacing of 0.1m should be maintained; cables above 10kV require a spacing of 0.25m. Control cables can be laid parallel without any gaps.
Extra care is required in special sections. Direct-buried cables crossing roads must be protected in protective conduits, extending at least 0.5m beyond the roadbed. When crossing oil and gas pipelines, fiberglass protective conduits should be used, maintaining a vertical clearance of 0.5m or greater.
02 Conduit Laying: The Professional Art of Cable Protection
Conduit laying provides a higher level of cable protection and is suitable for a variety of complex environments. This method effectively prevents mechanical damage, chemical corrosion, and other external factors from affecting the cables.
Applicable scenarios include where cables enter and exit buildings and structures, such as foundations, floors, and through walls; where cables pass through roads and are subject to mechanical damage; and where cables are drawn from the ground to 0.2 meters below ground level, where they are easily touched by people and may be subject to mechanical damage.
The selection of protective conduit is a critical step. The diameter of the protective conduit should meet the requirements of the power cable regulations and is generally 1.3-1.6 times the cable's outer diameter. For buried steel conduits, the burial depth should meet the design requirements, and the wall thickness should be greater than 2mm.
The inner diameter of the protective conduit should be no less than 1.5 times the cable's outer diameter.
Conduit installation regulations require that conduit openings should not be open and point vertically upward. Waterproof bends should be installed inside the box or at the end of the conduit. When conduit passes through an exterior wall, a waterproof sleeve should be installed and properly waterproofed.
Conduit openings entering distribution cabinets, desks, or boxes, if there is no bottom cover, should be 50-80mm above the foundation of the cabinet, desk, box, or panel.
The use of flexible conduit requires special attention. When connecting rigid conduit to electrical equipment and appliances via flexible conduit, the length of the flexible conduit should not exceed 0.5m in power engineering and 1.2m in lighting engineering.
Specialized connectors should be used to connect flexible metal or flexible conduit to rigid conduit or electrical equipment and appliances.
Regarding special environmental treatment, cables should be protected by conduit when passing through areas subject to vibration and pressure. Directly buried cables crossing railways or roads should be protected by protective conduit, extending 1m beyond the roadside or 0.5m beyond the drainage ditch.
03 Cable Tray Installation: Construction Standards for Aerial Cable Corridors
Cable trays provide safe and orderly overhead passages for cables and are widely used in modern buildings and industrial sites. Standardized cable tray installation not only ensures cable safety but also facilitates future maintenance and expansion.
Tray grounding is a critical step in ensuring safety. Metal ladders, trays, or troughs up to 30 meters in length must be reliably connected to the protective conductor at at least two points. For lengths exceeding 30 meters, additional connection points should be added every 20 to 30 meters.
Both the starting and ending ends must be reliably grounded.
Protective bonding conductors should be connected across both ends of the connecting plate between non-galvanized ladders, trays, and trough bodies. When no protective bonding conductor is connected across the galvanized ladders, trays, and trough bodies, each end of the connecting plate must have at least two connecting bolts with locknuts or washers.
Copper flexible conductors or braided copper wire with a cross-sectional area of at least 16 mm² should be used for connections at expansion joints or continuous hinged joints.
Cable laying regulations require that cables within a cable tray be arranged neatly and without crossing. Bends should adhere to the maximum allowable bend radius of the cable cross-section. Cables of different voltage levels should be laid in layers, with high-voltage cables on the upper layer.
When cables of the same voltage are laid along a support, the horizontal clearance should be no less than 35mm.
Regarding securing requirements, cables laid at an angle greater than 45 degrees in ladder racks, trays, or troughs should be secured to each support. Horizontally laid cables should have securing points at both ends, on both sides of bends, and every 5-10 meters.
Cables laid vertically or at an angle greater than 45 degrees in cable trenches or electrical shafts should be secured to each support.
Preventing common quality defects requires attention to several details. Avoid uneven lengths of cable tray supports and bent crossarms. Ensure that the cable tray is installed straight, free of twist, and with tight joints. Cable tray bends, tees, and other components should use pre-assembled components to ensure aesthetically pleasing connections and meet the minimum allowable cable bend radius.
After cable tray wiring is completed, the cable tray cover should be promptly installed.
Train tray identification is equally important. After the cables are laid, signboards should be hung at both ends of the cable bridge, at bends, intersections, and every 50 meters. Additional signboards should be installed on straight sections. The signboards should clearly indicate the cable number, starting and ending points, specifications, model, and voltage level. The markings should be clear and non-fading.
04 Quality Control and Common Problem Prevention
Quality control of cable laying must be implemented throughout the entire process, before, during, and after construction. Only by strictly controlling every step can the safe and stable operation of the cable line be ensured.
Pre-construction preparations include cable inspection and quality control. Before laying, insulation testing and withstand voltage testing must be performed. For cables below 1kV, insulation resistance between lines and to ground must be measured with a 1kV megohmmeter and should be no less than 10MΩ.
Also, ensure that the cable model and specifications meet the design and that the cable is visually inspected for damage.
Process monitoring requires careful attention to several details. The cable bend radius must be ≥15 times the outer diameter, and the bend radius of the protective conduit must be ≥20 times the outer diameter. A 1.5-meter margin should be reserved for intermediate joints, and U-shaped laying should be used to minimize thermal expansion and contraction.
Mechanical traction speed should be ≤15 m/min, traction force should be controlled at ≤7 N/mm², and anti-twist devices should be used to prevent cable twisting.
To prevent common problems, permanent marker posts should be installed every 50-100 meters for direct-buried cables. Backfill soil should be compacted layer by layer, and a warning tape with text should be laid on top.
Cable laying must be free of defects such as twisting, armor flattening, sheath fracture, and severe surface scratches.
Special environmental measures include: In cold regions, cables laid directly underground outdoors should be buried below the permafrost layer. When deep burial is not possible due to conditions, measures should be taken to prevent cable damage.
Where cables run parallel to or intersect with industrial water pipes or trenches, a clearance of at least 500 mm is recommended.
Standardized cable laying procedures are the cornerstone of ensuring the safe and stable operation of power systems. Whether direct burial, conduit, or cable tray installation, each method has its irreplaceable value and rigorous technical standards.
Construction details determine cable lifespan, and standardized procedures prevent potential risks. When technicians strictly adhere to these specifications, cable systems can provide reliable and safe power service in a variety of environments.
As the renowned architect Ludwig Mies van der Rohe said, "God is in the details." This philosophy also applies to cable installation—professionalism is reflected in every compliant bend radius, every reliable grounding connection, and every standard marking.